FSU Torches florida state university
Finance and Administration Florida State University
FSU Facilities
109 Mendenhall Building A
Tallahassee, Florida 32306-4152

Phone: 644-2843
Fax: 644-8351
       

 



 

policies and procedures logo  FSU Online Policies & Procedures


OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS

SPECIFIC AUTHORITY
Sections 240.209(3)(p), 1001.74, 1013.46, F. S.

OBJECTIVE
To establish procedures for the administration of construction manager agreements, including negotiation, contracting and payments.

OVERVIEW
This document describes contract administration procedures for Construction Manager agreements, including negotiations for pre-construction services and for the Guaranteed Maximum Price; amendments and change orders; approval of pay requests; subcontractor pre-qualification and bidding.

A. SCHEDULING THE NEGOTIATION
Upon approval of the construction manager selection as described in FSU Online Policies and Procedure OP-B-11-C2, Construction Managers Selection Process, the Facilities Design and Construction Office (FDC) schedules the negotiation meeting with representatives of the construction manager. The FDC transmits to the construction manager the standard Agreement between Owner and Construction Manager, the Project Manual, the Supplementary General Conditions for Construction Manager Agreements, applicable Supplements to the Project Manual and the link to download this procedure document. FDC directs the construction manager to prepare a proposal for pre-construction services in accordance with the "Guidelines for Construction Managers for the Preparation of Proposals for Pre-construction Services" (forms section).

B. NEGOTIATION FOR PRE-CONSTRUCTION SERVICES
Representatives of the FDC meet with the construction manager to negotiate the pre-construction portion of the contract.

If negotiations with the first ranked firm are unsuccessful, negotiations with that firm may be terminated and negotiations may be commenced with the second ranked firm. If negotiations with the second ranked firm are unsuccessful, the negotiations with that firm may be terminated and begun with the third ranked firm. If negotiations with the third ranked firm are unsuccessful, negotiations with the third ranked firm may be terminated and additional firms from the original pool may be selected or the project may be re-advertised. At any time during the negotiation process, negotiations may be terminated entirely and the use of construction management for the project may be reconsidered.

1. Preparation of agreement
Upon completion of successful negotiations, the FDC prepares the Agreement between Owner and Construction Manager. After approval by the University General Counsel, the FDC transmits five (5) copies of the agreement to the construction manager for execution.
 
2. Distribution of executed agreement
Upon final execution of the agreement by the University President, copies of the agreement are distributed as follows: the construction manager, the FDC, the University Accounting Office (2) and the architect/engineer.
 
3. Pre-construction agreement file
The FDC maintains a pre-construction agreement file containing: the pre-construction agreement, the pre-construction fee proposal and any additional information related to the pre-construction negotiation.

C. NEGOTIATION OF GUARANTEED MAXIMUM PRICE (GMP)
When it is time for the construction manager to develop the GMP proposal, the project manager directs the construction manager to prepare it in accordance with the "Guidelines for Construction Managers for the Preparation of Guaranteed Maximum Price Proposals" (forms section).

After the construction manager develops the GMP, the FDC reviews the proposal. The project manager ensures that the architect/engineer receives a copy for review and obtains a written recommendation from the architect/engineer that the GMP be accepted. When all parties have reviewed the GMP proposal, the project manager schedules the negotiation meeting.

If negotiations regarding the terms of the GMP proposal are unsuccessful, the FDC may terminate negotiations with that firm and begin negotiations with the second ranked firm from the original selection. If negotiations with the second ranked firm are unsuccessful, the FDC may terminate negotiations with that firm and begin negotiations with the third ranked firm from the original selection. If negotiations with the third ranked firm are unsuccessful, the FDC may terminate negotiations with the third ranked firm and may select additional firms from the original pool or re-advertise the project. At any time during the negotiation process, the FDC may terminate negotiations entirely and reconsider the use of construction management for the project or may re-advertise the project.

D. PREPARATION OF THE GMP AMENDMENT
Upon successful negotiation of the GMP, the FDC prepares the GMP amendment to the Agreement between Owner and Construction Manager. The amendment shall establish the GMP amount, the number of calendar days for completion and the liquidated damages amount (see FSU Online Policies and Procedures OP-B-11-E, Establishment of Construction Contract Time and Liquidated Damages) and shall reference any applicable supplements to the Project Manual. The FDC also prepares the Performance Bond and the Labor and Materials Payment Bond.

E. TRANSMITTAL OF AMENDMENT TO CONSTRUCTION MANAGER
After approval by the University General Counsel, the FDC transmits five (5) copies of the amendment to the construction manager, together with five (5) copies each of the Performance Bond and Labor and Materials Payment Bond, for execution. An example transmittal letter is included in the forms section.

F. REVIEW OF INSURANCE ISSUES
Upon receipt of the signed amendment, insurance certificates and bonds from the construction manager, the FDC will provide the Insurance Consultant (if such services are being provided on the project) with insurance documents for review. If an Insurance Consultant is not providing service on the project, the FDC reviews the bonds and insurance for compliance with the specifications.

G. DISTRIBUTION OF EXECUTED GMP AMENDMENT
Upon final execution of the GMP amendment by the University President, the amendment is distributed (each with a set of bonds), as follows: the construction manager, the FDC, the University Accounting Office, (2) and the architect/engineer.

H. GMP FILE
The FDC maintains a GMP file containing: the executed GMP amendment, the Performance and Payment Bonds, the insurance certificates, the approved GMP proposal, a recommendation letter from the architect/engineer, documentation of the approval of the bonds and insurance if reviewed by an insurance consultant, documentation of the calculation for liquidated damages and any correspondence related to the GMP.

I. 100% CONSTRUCTION DOCUMENTS
When the GMP was based on documents prior to the final 100% Construction Documents, the construction manager shall be required to execute a change order which accepts the 100% Construction Documents as the basis for construction. If there are scope increases between the 100% Construction Documents and the documents on which the GMP was based, those shall be addressed in the change order.

J. BIDDING SCHEDULE
The project manager discusses the bidding schedule with the construction manager. Based on the proposed schedule, the FDC develops a payment schedule with the architect/engineer for the architect/engineer's bidding phase payments.

K. PRE-QUALIFICATION OF SUBCONTRACTORS
The construction manager develops procedures for pre-qualification of trade contractors and coordinates with the FDC to ensure that the procedures are acceptable.

L. BID OPENINGS AND AWARD RECOMMENDATIONS
The project manager ensures that the construction manager publicly advertises for each bid package. While the bid openings are not required to be public, a university representative, generally the project manager, must be present when they are opened by the construction manager.

The project manager instructs the construction manager to provide the recommendation for award of each bid package, the recommendation from the architect/engineer, a copy of the bid tabulation form and a copy of each bid proposal.

M. CONSTRUCTION MANAGER INVOICES AND PAY REQUESTS
During the pre-construction and construction phases, the construction manager is paid as provided for in "Invoicing Procedures" (forms section).

N. REQUESTS FOR SELF-PERFORMANCE
If the construction manager makes a request to self-perform any portion of the work, the request is handled as described in "Procedures for Self-Performance of Work" (forms section).

O. CONSTRUCTION MANAGER'S CONTINGENCY AUTHORIZATIONS
The GMP includes a contingency amount for the construction manager's use as described in the Agreement between Owner and Construction Manager. The project manager must approve a CM Contingency Authorization for all expenditures of this contingency. These expenditures are to be supported by detailed breakdowns, including labor and material costs.

P. CHANGE ORDERS
Prior to approval, change orders must be supported by bids or by the unit prices established in the original bid. The CM markup on the change order will be limited to the percentage of profit approved in the original GMP. If changes are funded from bid savings, they are not eligible for a CM markup until the originally contracted GMP amount has been exceeded.

FORMS
Guidelines for Construction Managers for the Preparation of Proposals for Pre-Construction Services
Guidelines for Construction Managers for the Preparation of Guaranteed Maximum Price Proposals
Example Transmittal Letter
Invoicing Procedures
Procedures for Self-Performance of Work